Triple constraint: scope, time, and cost interact, with quality shaped by all three.
-
Life cycle: initiation planning execution monitoring/control closure.
-
WBS: hierarchical decomposition of total deliverable scope; charter: formally authorizes the project.
-
CPM: forward pass, backward pass, float, and continuous zero-float critical path; the longest valid path sets minimum duration.
-
PERT: and ; path-level probability assumptions matter.
-
Resource smoothing remains within float; leveling may extend the project.
-
EVM: , , , and . An index below one is unfavorable.
-
BATNA: best alternative if negotiation fails; never accept a deal worse than the applicable reservation point.
-
Monitoring continuously tracks delivery; evaluation periodically judges relevance, effectiveness, efficiency, sustainability, and impact.
-
TQM: customer focus, employee involvement, process thinking, evidence, integration, leadership, and continuous improvement.
-
PDCA: plan do check act; DMAIC: define measure analyze improve control.
-
ISO 9001: a requirements standard for a quality management system, built around seven quality-management principles.