Skip to content

Gantt Charts, Resources, and Earned Value

A Gantt chart is a time-scaled horizontal bar chart in which each activity is shown against its planned start, finish, and often its actual progress.

Illustrative Gantt chart for five activities over six weeks

Illustrative Gantt chart for five activities over six weeks

AdvantagesLimitations
Easy for stakeholders to readDense projects can become visually complex
Communicates planned dates and overlapDependencies may be hidden unless explicit links are added
Supports progress and milestone trackingA basic chart does not calculate the critical path
Useful for coordination and reportingResource conflicts are not automatically resolved
Can show baseline versus actual positionFrequent change requires disciplined updating and version control

Strengths and limitations of a Gantt chart

FeatureGantt chartCPM/PERT network
Visual basisTime-scaled barsNodes and precedence arrows
DependenciesOptional or less prominentExplicit and central
Critical pathMay be highlighted after calculationDerived from the network
Best useCommunication and time trackingLogical and quantitative analysis

Gantt and network views are complementary

Project scheduling requires activity identification, duration estimation, precedence logic, resource assignment, calendar constraints, milestone setting, and a time-scaled baseline. A mathematically feasible network may still be impossible if two simultaneous activities demand the same unavailable resource.

Resource leveling adjusts activity timing to remove resource over-allocation. It can move activities beyond available float and therefore may extend the critical path and project completion date.

Resource smoothing shifts activities only within existing float so that a fixed project completion date is preserved. It improves the resource profile but may not remove every overload.

MethodActionLikely effect
Delay non-critical workMove an activity into unused floatCompletion may remain unchanged
Activity splittingInterrupt and resume work where technically feasibleMore coordination and setup cost
Resource smoothingShift only within floatDeadline unchanged; overload may remain
Resource levelingReschedule according to constrained resource availabilityDeadline may move
Add or substitute resourcesIncrease capacity, overtime, subcontract, or alter methodHigher cost or quality/risk implications

Methods for resolving resource conflicts

If activities B and C both require one crane in week 3, first compare their float and priority. Move the activity with usable float; if both are critical, add capacity, change sequence or method, or accept a later finish through formal change control.

Earned Value Management (EVM) integrates scope, schedule, and cost by expressing planned work, completed work, and actual expenditure in the same monetary units at a defined status date.

MeasureFormulaInterpretation
Planned value (PV)Budgeted cost of scheduled workBudgeted value of work planned by the status date
Earned value (EV)Budgeted cost of work performedBudgeted value of work actually completed
Actual cost (AC)Actual cost of work performedCost actually incurred for completed work
Cost variance (CV)EV−ACEV-ACNegative means over budget
Schedule variance (SV)EV−PVEV-PVNegative means less work than planned
Cost performance index (CPI)EV/ACEV/ACBelow 1 means cost inefficiency
Schedule performance index (SPI)EV/PVEV/PVBelow 1 means behind the planned work rate

Core earned-value quantities and indicators